Thrivent Build Schedule updated 3/12/2010
316 Todd Street, Belmont
February 7 - Ground Breaking Ceremony
March 20 - Framing Day 1/Shed
* Tools helpful to bring: Hammer, nail apron, chalk line, electric saws, pencils and ladders
March 27 - Framing Day 2/Roofing Trusses/Sheathing/Shed
* Tools helpful to bring: Hammer, nail apron, chalk line, gloves and ladders
April 3 - Roofing Shingles
* Tools helpful to bring: Hammer, nail apron, chalk line, ladders and gloves.
April 10 - Siding
* Tools helpful to bring: Hammer, ladder, nail apron, nail sets, pencils, gloves and ladders. Long sleeved shirt for insulation.
April 17 - Interior and Exterior Trim
* Tools helpful to bring: miter box, hammer, nail aprons, nail set, pencil, ladder and gloves.
April 24 - Paint Day 1
* Tools helpful to bring: paint brushes, rollers, paint trays, buckets, ladders, caulking gun and gloves.
May 1- Paint Day 2/Landscaping/Punch List
* Tools helpful to bring: shovels, rakes, wheelbarrows, spreaders, gloves. Clean interior and wash windows inside and out, etc..
May 16 - Dedication
Habitat Office 704-864-6536
Carolyn - Extension 100 ~ Mary - Extension 103